- Thanks to the constantly strengthened production potential, the latest confirmation of which is, among other things, the efficiently and timely completed contract related to the expansion of PERN fuel depots, we are embarking on another task - says Jacek Szymanek, President of the Management Board of Mostostal Płock. The guarantee of the highest quality of our realizations is our long-standing work for PKN Orlen, with whom we signed another contract in early April.

Contract value: PLN 104.8 million net;
Payment term: 45 days from the date of delivery of a properly issued invoice to the Purchaser;
Performance bond: 5% of the net remuneration paid in the form of a bank or insurance guarantee.

Attachments

Disclaimer

Mostostal Plock SA published this content on 19 April 2023 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 19 April 2023 10:09:24 UTC.