Pan African Resources PLC                                                            
    (Incorporated and registered in England and Wales under Companies Act 1985 with      
    registered number 3937466 on 25 February 2000)                                       
    AIM Code: PAF                                                                        
    JSE Code: PAN                                                                        
    ISIN: GB0004300496                                                                   
    ('Pan African' or 'the Group')                                                       

                                  OPERATIONAL UPDATE                               

    Pan African, the African-focused precious metals producer, is pleased to
    provide an operational update for the year ended 30 June 2017 ('current
    reporting period').

    KEY FEATURES AND HIGHLIGHTS

      * Gold produced for the current reporting period was approximately 173koz,
        4.4% below the production guidance provided. This was due to the slower
        than anticipated restart of the underground mine at Evander Gold Mining
        Proprietary Limited ('Evander Mines') and operational challenges
        experienced at Barberton Mines Proprietary Limited ('Barberton Mines'),
        which have now been remedied.
      * Evander Mines 7 shaft refurbishment has been successfully completed, and
        the restructuring programme is materially complete.
      * Elikhulu Tailings Retreatment Plant ('Elikhulu') is fully funded and
        construction on-track.
      * Feasibility study completed for a sub-vertical shaft at the high-grade
        Fairview mining operation at Barberton Mines, with an estimated capital
        expenditure of R105 million, to be spent over a two year period. This
        project should yield an additional 7-10koz of gold per annum.
      * Encouraging high grade drill result at Evander Mines' 2010 Pay Channel
        orebody, which has prompted a feasibility study to assess the economic
        viability of expanding the underground mining operations.
      * Completion of disposal of Uitkomst Colliery Proprietary Limited ('Uitkomst
        Colliery') on 30 June 2017.
      * Strong statement of financial position with net debt of R66.7 million at 30
        June 2017 (30 June 2016: R339.7 million) and available debt facilities of
        R880.2 million.
      * Production guidance for the 2018 financial year in excess of 190koz.

    CEO STATEMENT

    Cobus Loots, the CEO of Pan African, commented:  "The 2017 financial year was
    operationally challenging in many respects, however the Group is now seeing the
    benefits of the remedial actions implemented by management.   We look forward
    to a much improved performance in 2018, with a substantial increase in gold
    production.  The Elikhulu project is on track for delivering first gold as
    originally planned, and is expected to contribute low-cost ounces and profits
    in the next 18 months.  We are excited about the prospects for the Evander
    Mines' 2010 Pay Channel project; the Evander Mines team now has to bring the
    project to account in the near term, in a profitable and value-accretive
    manner.  During the past year, Pan African has reaffirmed our gold focus and
    again delivered transactions that crystallise shareholder value."

    PRODUCTION PERFORMANCE AND 2018 GUIDANCE

    Pan African's gold production for the current reporting period was 4.4% below
    its revised gold production guidance (announced on 20 February 2017) at
    approximately 173Koz. As per the announcements of 10 March 2017 and
    10 April 2017, the Group is pleased to report that the initial Evander Mines
    shaft refurbishment has been successfully completed, and the restructuring
    programme is materially complete. This will result in substantial cost savings
    going forward.

    In the next financial year, the following initiatives will continue at Evander
    Mines to ensure a sustainable and consistent performance from the operation:

      * Continuation of the engineering work plan to improve the reliability of the
        shaft and related infrastructure, including:
          + 8 Shaft pump column;
          + 7 Shaft steelwork i.e. buntons and guides; and
          + 7a and 8 Shaft, shaft bottom arrangements.
      * Improving the total meters squared blasted per panel and per crew.
      * Clean mining programme:
          + Stoping width reduction, with the introduction of improved hanging wall
            support;
          + Improved fragmentation resulting from optimisation of the blast design;
            and
          + Improve quality of sweepings with the introduction of user-friendly
            blasting barricades and additional sweeping tools.
      * Old gold vamping, which is the cleaning of mud accumulations in redundant
        declines and spillage in and around the belt declines.
      * Pillar mining and vamping at 7 Shaft.

    Mining in the high-grade areas in Fairview's 11-block is also now established
    and expected to continue for the remainder of the 2018 financial year.
     Productivity improvements are expected at Fairview following the commissioning
    of a new bulk air cooler, which will reduce the ambient temperature at the work
    face by approximately 3 to 4 degrees Celsius. To address the flexibility
    constraints currently experienced at Fairview, and increase gold production
    from this very high-grade and long life ore-body, a feasibility study into a
    new sub-vertical shaft has been finalised. The findings of the feasibility
    study are detailed in the growth projects section below.

    The Group's gold production guidance for the financial year ending 30 June 2018
    is in excess of 190Koz, an increase of approximately 10% on 2017 gold
    production.

    GROWTH PROJECTS

    ELIKHULU PROJECT UPDATE

    The Elikhulu project is progressing according to plan with project completion
    and first gold expected in the last quarter of the 2018 calendar year.
    Following the successful US$50 million equity raise on 12 April 2017, Pan
    African has commenced funding the initial capital expenditure on the Elikhulu
    project's civil engineering works and the procurement of long-lead-time items,
    such as the tower crane and the carbon-in-leach tanks, which are critical to
    ensuring construction deadlines are met.

    Capital expenditure of approximately R175 million has been incurred on the
    Elikhulu project during the current reporting period, and capital spend remains
    on track relative to the total initial forecast capital expenditure of R1.74
    billion.

    Pan African is also pleased to announce that the facility agreement for the R1
    billion Elikhulu term debt facility has been signed. The facility was
    underwritten by Rand Merchant Bank, a division of FirstRand Bank Limited, and
    the syndication has closed successfully, with an over-subscription of more than
    50%. The appetite shown by the banking market highlights the quality of the
    project, which prevailed despite the negative sentiment at the time of the
    release of the new Mining Charter. Utilisation of the facility is subject to
    the fulfilment of customary conditions precedent, and the first drawings under
    the seven-year facility are scheduled for the final quarter of the 2017
    calendar year.

    Together with the Group's existing R1 billion revolving credit facility, these
    facilities comprise the core debt instruments for funding the Group's capital
    expenditure programmes. The low-cost, long-life Elikhulu project is expected to
    increase the Group's annual gold production by more than 50koz per annum and
    reduce the Group's average all-in cost of production.

    BARBERTON MINES SUB-VERTICAL SHAFT PROJECT AT FAIRVIEW

    The Fairview mining operation is currently restricted by the hoisting capacity
    of its No.3 Decline, which is used to access workings below 42 Level.  This
    decline is currently used to transport employees, material, and for rock
    hoisting.  The 11-block, or MRC, orebody has an average grade of 31.3 g/t and
    current life-of-mine of 22 years.  With no intervention, future mining at depth
    will result in increased travelling distance, reduce employee face time and
    cause a lack of capacity to ensure both ore replacement and exploration
    development.

    Pan African, with the assistance of DRA Projects SA Proprietary Limited
    ('DRA'), has completed a feasibility study on the construction of a
    raise-bored, sub-vertical shaft from Fairview's' 42 Level to 64 Level, with the
    potential of continuing the vertical shaft in future to 68 Level.  This
    sub-vertical shaft will be used to transport employees and material to the
    working areas, which will allow the No.3 Decline to be used exclusively for
    rock hoisting, increasing overall capacity and production from this mining
    area.

    DRA has reviewed the technical and commercial aspects of the project and the
    supporting feasibility study has yielded very positive results. The estimated
    capital expenditure for the project, including contingencies, is approximately
    R105 million, to be incurred over a two-year period. The productivity
    improvements for Fairview are estimated to yield an additional 7,000oz of gold
    per annum, which can be optimised further to more than 10,000oz per annum.

    EVANDER MINES 7 SHAFT NO. 3 DECLINE AND 2010 PAY CHANNEL

    The 2010 Pay Channel resource is adjacent to the 7 Shaft infrastructure and
    extends from the boundary of Taung Gold International Limited's 6 Shaft project
    and mining rights.  As previously reported, Evander Mines embarked on an
    exploration programme to drill a further exploration borehole from surface, to
    increase geological confidence in the 2010 Pay Channel orebody, for which
    resources are summarised in the table below:

      7 Shaft: No.3 Decline and 2010 Pay Channel  
                      resources                   
                                                  
     Category    Tonnes   Grade   Contained gold  
                                                  
                million    g/t    tonnes     Moz  
                                                  
    Measured        0.52   11.02      5.80    0.19
                                                  
    Indicated       0.34   10.02      3.50    0.11
                                                  
    Inferred        5.41   10.85     58.70    1.89
                                                  
    Total           6.27   10.82     68.00    2.19

    On 6 July 2017, the exploration borehole successfully intersected the Kimberley
    reef at a depth of approximately two kilometres, highlighting a reef
    intersection with a 6cm width at 36.8g/t. Additional drilling deflections will
    be performed to further delineate the ore body.  The previous borehole into the
    2010 Pay Channel yielded a reef intersection with a 49 cm width at 36.04g/t.

    Harmony Gold Mining Company Limited previously developed the 7 Shaft mine
    workings towards the 2010 Pay Channel, however due to financial constraints and
    a reassessment of capital priorities, all development on the Evander Mines'
    shafts (other than 8 Shaft) was halted in 2009. This resulted in the controlled
    flooding of the development ends and 7 Shaft's No.3 Decline, from 22 level up
    to 18 Level. Following the dewatering, only standard footwall and on-reef
    development would need to be completed, with the associated engineering
    infrastructure, before mining can commence.

    The 2010 Pay Channel is approximately three kilometres in tramming distance
    from 7 Shaft, which is currently used by Evander Mines for hoisting to the
    Kinross metallurgical plant. This compares favourably with the 8 Shaft mining
    areas, which are approximately 10 kilometres in tramming distances from 7
    Shaft.

    The Pan African project team has commenced a feasibility study related to the 7
    Shaft No.3 Decline and 2010 Pay Channel resource, which will address the
    following critical issues:

      * Collation of geological data from the drill hole intersection and
        deflections;
      * The cost and timing of dewatering and re-equipping the 7 Shaft No.3 Decline
        from 18 Level to 22 Level;
      * The development cost and timing to access the 2010 Pay Channel; and
      * The economic viability of the project.

    The 2010 Pay Channel can potentially increase Evander Mines' underground gold
    production significantly at a relatively low capital cost, using Evander Mines'
    established shaft and metallurgical facilities.  The feasibility study for the
    project is expected to be completed during Q1 2018.

    DISPOSAL OF UITKOMST COLLIERY

    The Uitkomst Colliery disposal to Coal of Africa Limited ('CoAL') became
    effective on 30 June 2017 ("effective date"). On the effective date CoAL took
    ownership, control and management of Pan African Resources Coal Holdings
    Proprietary Limited, the holding company of Uitkomst Colliery. Pan African
    received its consideration on conclusion of the disposal on the effective date
    as follows:

      * R125 million in cash
      * R125 million through the issue of 261,287,625 new ordinary shares in CoAL
      * R25 million in interest bearing deferred consideration which may be paid by
        CoAL at any time prior to the second anniversary of the effective date.

    GROUP NET DEBT POSITION AND INVESTMENTS

    The Group's statement of financial position is robust with net debt at 30 June
    2017 of R66.7 million
    (30 June 2016: R339.7 million). Available debt facilities at 30 June 2017 were
    R880.2 million (30 June 2016: R624.6 million).

    The Group net debt is comprised of R161.2 million in cash and cash equivalents,
    and R227.9 million of drawn debt facilities.

    The groups holding in CoAL shares, which is classified as an investment, was
    valued at approximately R127.5 million at 30 June 2017.

    FINAL RESULTS

    The final audited results for the year ended 30 June 2017 are expected to be
    published on or about
    20 September 2017.

    Shareholders are advised that the financial information contained in this
    announcement has not been reviewed or reported on by Pan African's external
    auditors.

    By order of the Board

    Johannesburg

    20 July 2017

    Contact information                                                        
                                                                               
                                                                               
    Corporate Office                      Registered Office                    
    The Firs Office Building              Suite 31, Second Floor               
    1st Floor, Office 101                 107 Cheapside                        
    Cnr. Cradock and Biermann Avenues     London                               
    Rosebank, Johannesburg                EC2V 6DN                             
    South Africa                          United Kingdom                       
    Office:  + 27 (0) 11 243 2900         Office:  + 44 (0) 207 796 8644       
    Facsimile: + 27 (0) 11 880 1240       Facsimile: + 44 (0) 207 796 8645     
                                                                               
    Cobus Loots                           Deon Louw                            
    Pan African Resources PLC             Pan African Resources PLC            
    Chief Executive Officer               Financial Director                   
    Office: + 27 (0) 11 243 2900          Office: + 27 (0) 11 243 2900         
                                                                               
                                                                               
    Phil Dexter                           John Prior / Paul Gillam             
    St James's Corporate Services Limited Numis Securities Limited             
    Company Secretary                     Nominated Adviser and Joint Broker   
    Office: + 44 (0) 207 796 8644         Office: +44 (0) 20 7260 1000         
                                                                               
                                                                               
    Sholto Simpson                        Matthew Armitt / Ross Allister       
    One Capital                           Peel Hunt LLP                        
    JSE Sponsor                           Joint Broker                         
    Office: + 27 (0) 11 550 5009          Office: +44 (0) 207 418 8900         
                                                                               
                                                                               
    Julian Gwillim                        Jeffrey Couch/Neil Haycock/Thomas    
    Aprio Strategic Communications        Rider                                
    Public & Investor Relations SA        BMO Capital Markets Limited          
    Office: +27 (0)11 880 0037            Joint Broker                         
                                          Office: +44 (0) 207 236 1010         
                                                                               
                                                                               
    Bobby Morse/Chris Judd                                                     
    Buchanan Communications                                                    
    Public & Investor Relations UK                                             
    Office: +44 (0) 207 466 5000                                               

    http://www.panafricanresources.com/