Theolia SA has signed a contract for the purchase of nine wind turbines for the Chemin Perre project, located on the Nogentais community of communes, on the territory of the towns of Montpothier and Villenauxe-la-Grande, in the Aube French department. The contract also includes associated maintenance services, securing the costs of maintenance over fifteen years. The unit capacity of the selected wind turbine model reached 2 MW, bringing the total installed capacity of the wind farm to 18 MW.

The future wind farm will generate green electricity that will cover the domestic electricity needs of approximately 21,000 households each year. Construction works will start in the second half of 2015 and commissioning is expected during the second half of 2016.